Capital Improvement Program
Click here to view projects currently out to bid.
The Capital Improvement Program (CIP) includes short and long-term projects to maintain or rehabilitate the City's streets, storm drains, sewer system, water system, cable service and government-owned buildings. While funds are appropriated on an annual basis, the program encompasses a five-year period.
Projects Under Construction
Facilities | Streets | Stormwater | Water | Wastewater
| Project # | 84210 | |||
| Project Manager | Harry Burrowes, (650) 616-7066 | |||
| Contractor | BKF, Inc. (engineering design firm) | |||
| Description | Please CLICK HERE to visit the Crestmoor Neighborhood Rebuiling Project website. |
|||
Back to Projects Under Construction
| FACILITIES |
| Project # | 83710 | |||
| Project Manager | Will Anderson, (650) 616-7052 | |||
| Contractor | Interstate Grading & Paving, Inc. | |||
| Description | This project will install a synthetic grass field at Lions Field. This new surface allows for three months of additional use of the area each year by eliminating the need to close the field annually for turf restoration and reseeding. The site will be used for baseball, youth and adult softball, soccer, youth and adult flag football, Pop Warner football practice, and lacrosse. In addition, the project will make drainage improvements to the site necessary for synthetic turf and improve ADA access.
|
|||
| Status | Completed rough grading and drainage improvements. Work continues on installation of electrical and irrigation lines, and construction has started on the new fence. |
|||
| Est. Completion Date | June 2012 | |||
Upated 04/06/12
| STREETS |
| Project # | 82707 | |||
| Project Manager | Project managed by Caltrain. Please contact (650) 508-7726 for more information. | |||
| Contractor | Granite Construction | |||
| Description | This project is administered by Caltrain and will elevate the Caltrain train tracks throughout much of San Bruno. The City of San Bruno has retained a construction manager to monitor construction activities and ensure that the project is completed to the City's expectations.
|
|||
| Status | The anticipated operations for the week of May 14th are as follows: Crews will continue installing temporary piling and shoring within the Caltrain right-of-way during the day, excavating soil, and placing lightweight cellular concrete fill in preparation for placing the retaining wall panels. Crews will continue placing concrete at the San Bruno and San Mateo Grade Separation abutments and center bents. Rebar and formwork has also begun at Angus Avenue. Sidewalk work will continue along San Mateo Avenue. The contractor will install and maintain storm water pollution measures throughout the project. Night Work: Traffic Conditions: Noise / Air Quality: Utility Relocation: Public Notification: |
|||
| Est. Completion Date | December 2012 | |||
Updated 04/23/12
| Project # | 83904 |
|
||
| Project Manager | Will Anderson, (650) 616-7052 | |||
| Contractor | J.J. Nguyen, Inc. of San Jose | |||
| Description | This project will remove and replace hardscape surfacing, irrigation lines, and landscaping within six existing medians along El Camino Real. After project completion, twelve of the sixteen medians on El Camino Real will be complete. |
|||
| Status | Currently undergoing construction startup. Construction scheduled to begin in April 2012. | |||
| Est. Completion Date | October 2012 | |||
| Project # | 83705 |
|
||
| Project Manager | Nader Dahu, (650) 616-7047 | |||
| Contractor | Installation performed by City of South San Francisco | |||
| Description | This project will install new pedestrian push button stations with audible notification at key intersections along El Camino Real. |
|||
| Status | Installation scheduled for May through June. | |||
| Est. Completion Date | May 2012 | |||
Back to Projects Under Construction
| STORMWATER |
| WATER |
Back to Projects Under Construction
| WASTEWATER |
| Project # | 85707-A |
|
||
| Project Manager | Wing Wong, (650) 616-7043 | |||
| Contractor | Installation performed by City of South San Francisco | |||
| Description | This project will construct approximately 150 feet of 18-inch diameter high-density-polyethylene (HDPE) sewer main from the last manhole at Kains Avenue west of San Mateo Avenue and connect to a new manhole on Huntington Avenue. A second construction phase will occur in the near future to replace longer sections of sewer main on Kains Avenue. |
|||
| Status | Contract awarded 3/27/2012. Construction to start in May 2012. | |||
| Est. Completion Date | July 2012 | |||
Back to Projects Under Construction
The process invloved in managing a project from conception to final closeout often requires many steps. For example, some complex projects--such as a sewer main replacement or building construction--may require the expertise of civil engineers specializing in the design of those types of projects. Once fully designed, most projects then undergo a public bidding process to award a construction contract to the lowest responsible bidder. After the public bidding process ends, the City Council awards the contract and staff works to ensure that the necessary paperwork and insurance documents are complete. Only then can construction begin. Though sometimes lengthy, this process ensures residents receive well-executed projects in a cost-effecitve manner.
The Public Services Department is revising the way it will be reporting the status of projects in the deisgn phase. Please check back in the spring of 2012 for the new format.
Please contact the Engineering Division at (650) 616-7065 if you have any questions regarding the status or scope of these projects.