City of San Bruno
San Bruno images

Capital Improvement Program
Click here to view projects currently out to bid.

The Capital Improvement Program (CIP) includes short and long-term projects to maintain or rehabilitate the City's streets, storm drains, sewer system, water system, cable service and government-owned buildings. While funds are appropriated on an annual basis, the program encompasses a five-year period.




Projects Under Construction
Facilities
| Streets | Stormwater | Water | Wastewater

Crestmoor Neighborhood Reconstruction Project
Project # 84210
   
Project Manager Harry Burrowes, (650) 616-7066
Contractor BKF, Inc. (engineering design firm)
Description

The Glenview Area Restoration Project will restore the public infrastructure that was damaged due to the PG&E gas main explosion that occurred on September 9,2010. The infrastructure to be restored includes roadway pavement, curb and gutter, sidewalk, water, sewer and storm drain system. It also includes restoration of a neighborhood park at the southeast corner of Glenview Drive and Claremont Drive.

With input from neighborhood residents, the project will restore the area's infrastructure to a higher level than what was present before the explosion.

A community meeting at the San Bruno Senior Center was held on July 27 at 7:00pm. To view a PDF of the presentation, please click HERE (large file).

Status Phase I sewer work is complete. A contract for Phase I water improvements was awarded January 24, 2012.
Est. Completion Date This project may be completed in phases over the next two years. The first phase of construction is underway. The schedule will be updated periodically..

Upated 01/27/12

Back to Projects Under Construction


FACILITIES

Back to Projects Under Construction


STREETS
Caltrain Grade Separation Project
Project # 82707    
Project Manager Project managed by Caltrain. Please contact (650) 508-7726 for more information.
Contractor Granite Construction
Description

This project is administered by Caltrain and will elevate the Caltrain train tracks throughout much of San Bruno. The City of San Bruno has retained a construction manager to monitor construction activities and ensure that the project is completed to the City's expectations.

Detailed project description

 

Status

The anticipated operations for the week of February 13th are as follows:

A crew will continue driving piles at San Bruno and start mobilizing at Angus once the existing rail and ties are removed. Granite will continue removing rail, ties, and ballast sections from the main line track between 380 and the old station within the temporary track area. A crew will continue excavating for the elevated track section. GCCI will excavate and prepare for pile driving at San Mateo Ave. Crews will continue demolishing the old station platform on the west side of the tracks and removing old light pole bases. A crew will continue installing the sanitary sewer pipe in Huntington at San Mateo. A crew will install ground water monitoring wells around the BART vent structure. Crews will install and maintain storm water pollution measures at various locations.

Night Work:
GCCI will continue removing rail, ties and ballast sections from the main line track within the temporary track area.

Traffic Conditions:
Flaggers will be on San Mateo at the yard entrance for truck ingress/egress and at the railroad crossing on San Mateo. Temporary lanes closures will be utilized on San Bruno Ave during the day for pile driving operations.

Noise / Air Quality:
The nighttime operation will not generate noise levels as loud as the existing train traffic and will not affect air quality standards.  Pile driving at San Bruno, San Mateo and Angus is continuing. The operation is limited to the hours of 9 am to 5 pm. This activity will be loud. The remaining daytime activities will be within the City noise and air quality limitations.

Utility Relocation:
AT&T will access manhole vaults in San Mateo and Montgomery to splice a new cable prior to removing the poles in front of Melody. AT&T is scheduled to remove the overhead cables and poles on San Mateo Ave adjacent to Melody Toyota. UCI is continuing to lower the fiber optic duct banks between San Bruno and San Mateo where the old main line tracks were located. Verizon is scheduled to continue relocation at San Mateo Ave at Huntington. PG&E is continuing to relocate electrical vaults and transformer in Posy Park.

Public Notification:
Caltrain is providing a weekly construction update posted on the Caltrain website.

Est. Completion Date December 2012

Updated 02/10/12

Street Rehabilitation Project
Project # 82666

 

   
Project Manager Tina Tseng, (650) 616-7157
Contractor A construction contract has not yet been awarded.
Description

This project involves the repair and preventative maintenance of local, collector and arterial streets based on street condition identified through the use of the City’s Pavement Management Program (PMP). The long-term goal is to achieve an average pavement condition index score equal to or greater than 70. The present average in the City is 63.

The City’s PMP is designed to maximize the longevity of streets with cost effective maintenance and repairs while working within budget constraints. By doing so, the infrastructure investment that the City has made in the street system over past years is preserved. Accelerated roadway deterioration leads to an increase in overall roadway maintenance costs. A street in good condition also prevents the formation of hazardous conditions such as potholes.

Below is a link showing the preliminary streets selected for treatment in Spring/Summer 2012. The street sections will get a crack seal, slurry seal, or complete repaving depending on their condition. The final list will be revised and confirmed prior to awarding a construction contract.

Preliminary Street Listing

Status Project under design.
Est. Completion Date Summer 2012

Updated 12/23/11

 

Back to Projects Under Construction

 

STORMWATER

Back to Projects Under Construction

WATER

Back to Projects Under Construction

WASTEWATER

 

Back to Projects Under Construction

 

 

Projects in Design

The process invloved in managing a project from conception to final closeout often requires many steps. For example, some complex projects--such as a sewer main replacement or building construction--may require the expertise of civil engineers specializing in the design of those types of projects. Once fully designed, most projects then undergo a public bidding process to award a construction contract to the lowest responsible bidder. After the public bidding process ends, the City Council awards the contract and staff works to ensure that the necessary paperwork and insurance documents are complete. Only then can construction begin. Though sometimes lengthy, this process ensures residents receive well-executed projects in a cost-effecitve manner.

The Public Services Department is revising the way it will be reporting the status of projects in the deisgn phase. Please check back by January 2012 for the new format.

Please contact the Engineering Division at (650) 616-7065 if you have any questions regarding the status or scope of these projects.

Back to Top


 
Email Page Print Page