City of San Bruno
San Bruno images

Capital Improvement Program
Click here to view projects currently out to bid.

The Capital Improvement Program (CIP) includes short and long-term projects to maintain or rehabilitate the City's streets, storm drains, sewer system, water system, cable service and government-owned buildings. While funds are appropriated on an annual basis, the program encompasses a five-year period.




Projects Under Construction
Facilities
| Streets | Stormwater | Water | Wastewater

Crestmoor Neighborhood Reconstruction Project
Project # 84210
   
Project Manager Harry Burrowes, (650) 616-7066
Contractor BKF, Inc. (engineering design firm)
Description

Please CLICK HERE to visit the Crestmoor Neighborhood Rebuiling Project website.

Upated 02/21/12

Back to Projects Under Construction


FACILITIES

Lions Field Synthetic Turf Project
Project # 83710
   
Project Manager Will Anderson, (650) 616-7052
Contractor Interstate Grading & Paving, Inc.
Description

This project will install a synthetic grass field at Lions Field. This new surface allows for three months of additional use of the area each year by eliminating the need to close the field annually for turf restoration and reseeding. The site will be used for baseball, youth and adult softball, soccer, youth and adult flag football, Pop Warner football practice, and lacrosse.

In addition, the project will make drainage improvements to the site necessary for synthetic turf and improve ADA access.

 

Status

Completed rough grading and drainage improvements. Work continues on installation of electrical and irrigation lines, and construction has started on the new fence.

Est. Completion Date June 2012

Upated 04/06/12

Back to Projects Under Construction


STREETS
Caltrain Grade Separation Project
Project # 82707    
Project Manager Project managed by Caltrain. Please contact (650) 508-7726 for more information.
Contractor Granite Construction
Description

This project is administered by Caltrain and will elevate the Caltrain train tracks throughout much of San Bruno. The City of San Bruno has retained a construction manager to monitor construction activities and ensure that the project is completed to the City's expectations.

Detailed project description

 

Status

The anticipated operations for the week of May 14th are as follows:

Crews will continue installing temporary piling and shoring within the Caltrain right-of-way during the day, excavating soil, and placing lightweight cellular concrete fill in preparation for placing the retaining wall panels. Crews will continue placing concrete at the San Bruno and San Mateo Grade Separation abutments and center bents. Rebar and formwork has also begun at Angus Avenue. Sidewalk work will continue along San Mateo Avenue. The contractor will install and maintain storm water pollution measures throughout the project.

Night Work:
The Contractor will be installing and removing temporary shoring within the Caltrain right-of-way in area from San Bruno to Angus where work cannot be done safely during the daytime hours due to the close proximity to the tracks.  

Traffic Conditions:
Flaggers will intermittently be on San Mateo Avenue at the yard entrance for truck ingress/egress and at the railroad crossings at Angus Avenue, San Bruno Avenue and San Mateo Avenue.  

Noise / Air Quality:
Operations will not generate noise levels as loud as the existing train traffic and will not affect air quality standards.  Daytime and nighttime activities will be within the City noise and air quality limitations.

Utility Relocation:
There is no utility work scheduled this week.

Public Notification:
Caltrain is providing a weekly construction update posted on the Caltrain website.

Est. Completion Date December 2012

Updated 04/23/12

Street Rehabilitation Project

Street Rehabilitation Project
Project # 82666

 

   
Project Manager Tina Tseng, (650) 616-7157
Contractor A construction contract has not yet been awarded.
Description

This project involves the repair and preventative maintenance of local, collector and arterial streets based on street condition identified through the use of the City’s Pavement Management Program (PMP). The long-term goal is to achieve an average pavement condition index score equal to or greater than 70. The present average in the City is 63.

The City’s PMP is designed to maximize the longevity of streets with cost effective maintenance and repairs while working within budget constraints. By doing so, the infrastructure investment that the City has made in the street system over past years is preserved. Accelerated roadway deterioration leads to an increase in overall roadway maintenance costs. A street in good condition also prevents the formation of hazardous conditions such as potholes.

Below is a link showing the preliminary streets selected for treatment in Summer 2012. The street sections will get a crack seal, slurry seal, or complete repaving depending on their condition. The final list will be revised and confirmed prior to awarding a construction contract.

Preliminary Street Listing

Status Project under design.
Est. Completion Date Summer 2012

Updated 04/06/11

El Camino Real Phase 2 Median Upgrade Project
Project # 83904

 

   
Project Manager Will Anderson, (650) 616-7052
Contractor J.J. Nguyen, Inc. of San Jose
Description

This project will remove and replace hardscape surfacing, irrigation lines, and landscaping within six existing medians along El Camino Real. After project completion, twelve of the sixteen medians on El Camino Real will be complete.

Status Currently undergoing construction startup. Construction scheduled to begin in April 2012.
Est. Completion Date October 2012

Updated 04/06/11

El Camino Real Pedestiran Improvements Project
Project # 83705

 

   
Project Manager Nader Dahu, (650) 616-7047
Contractor Installation performed by City of South San Francisco
Description

This project will install new pedestrian push button stations with audible notification at key intersections along El Camino Real.

Status Installation scheduled for May through June.
Est. Completion Date May 2012

Updated 04/12/11

 

Back to Projects Under Construction

 

STORMWATER

Back to Projects Under Construction

WATER

Back to Projects Under Construction

WASTEWATER
Kains to Angus Sewer Bypass Project
Project # 85707-A

 

   
Project Manager Wing Wong, (650) 616-7043
Contractor Installation performed by City of South San Francisco
Description

This project will construct approximately 150 feet of 18-inch diameter high-density-polyethylene (HDPE) sewer main from the last manhole at Kains Avenue west of San Mateo Avenue and connect to a new manhole on Huntington Avenue. A second construction phase will occur in the near future to replace longer sections of sewer main on Kains Avenue.

Status Contract awarded 3/27/2012. Construction to start in May 2012.
Est. Completion Date July 2012

Updated 04/12/11

 

Back to Projects Under Construction

 

 

Projects in Design

The process invloved in managing a project from conception to final closeout often requires many steps. For example, some complex projects--such as a sewer main replacement or building construction--may require the expertise of civil engineers specializing in the design of those types of projects. Once fully designed, most projects then undergo a public bidding process to award a construction contract to the lowest responsible bidder. After the public bidding process ends, the City Council awards the contract and staff works to ensure that the necessary paperwork and insurance documents are complete. Only then can construction begin. Though sometimes lengthy, this process ensures residents receive well-executed projects in a cost-effecitve manner.

The Public Services Department is revising the way it will be reporting the status of projects in the deisgn phase. Please check back in the spring of 2012 for the new format.

Please contact the Engineering Division at (650) 616-7065 if you have any questions regarding the status or scope of these projects.

Back to Top


 
Email Page Print Page