Capital Improvement Program
Click here to view projects currently out to bid.
The Capital Improvement Program (CIP) includes short and long-term projects to maintain or rehabilitate the City's streets, storm drains, sewer system, water system, cable service and government-owned buildings. While funds are appropriated on an annual basis, the program encompasses a five-year period.
Projects Under Construction
Facilities | Streets | Stormwater | Water | Wastewater
| Project # | 84210 | |||
| Project Manager | Harry Burrowes, (650) 616-7066 | |||
| Contractor | BKF, Inc. (engineering design firm) | |||
| Description | The Glenview Area Restoration Project will restore the public infrastructure that was damaged due to the PG&E gas main explosion that occurred on September 9,2010. The infrastructure to be restored includes roadway pavement, curb and gutter, sidewalk, water, sewer and storm drain system. It also includes restoration of a neighborhood park at the southeast corner of Glenview Drive and Claremont Drive. With input from neighborhood residents, the project will restore the area's infrastructure to a higher level than what was present before the explosion. A community meeting at the San Bruno Senior Center was held on July 27 at 7:00pm. To view a PDF of the presentation, please click HERE (large file). |
|||
| Status | Phase I sewer work is complete. A contract for Phase I water improvements was awarded January 24, 2012. | |||
| Est. Completion Date | This project may be completed in phases over the next two years. The first phase of construction is underway. The schedule will be updated periodically.. | |||
Back to Projects Under Construction
| FACILITIES |
Back to Projects Under Construction
| STREETS |
| Project # | 82707 | |||
| Project Manager | Project managed by Caltrain. Please contact (650) 508-7726 for more information. | |||
| Contractor | Granite Construction | |||
| Description | This project is administered by Caltrain and will elevate the Caltrain train tracks throughout much of San Bruno. The City of San Bruno has retained a construction manager to monitor construction activities and ensure that the project is completed to the City's expectations.
|
|||
| Status | The anticipated operations for the week of February 13th are as follows: A crew will continue driving piles at San Bruno and start mobilizing at Angus once the existing rail and ties are removed. Granite will continue removing rail, ties, and ballast sections from the main line track between 380 and the old station within the temporary track area. A crew will continue excavating for the elevated track section. GCCI will excavate and prepare for pile driving at San Mateo Ave. Crews will continue demolishing the old station platform on the west side of the tracks and removing old light pole bases. A crew will continue installing the sanitary sewer pipe in Huntington at San Mateo. A crew will install ground water monitoring wells around the BART vent structure. Crews will install and maintain storm water pollution measures at various locations. Night Work: Traffic Conditions: Noise / Air Quality: Utility Relocation: Public Notification: |
|||
| Est. Completion Date | December 2012 | |||
Updated 02/10/12
Back to Projects Under Construction
| STORMWATER |
| WATER |
Back to Projects Under Construction
| WASTEWATER |
Back to Projects Under Construction
The process invloved in managing a project from conception to final closeout often requires many steps. For example, some complex projects--such as a sewer main replacement or building construction--may require the expertise of civil engineers specializing in the design of those types of projects. Once fully designed, most projects then undergo a public bidding process to award a construction contract to the lowest responsible bidder. After the public bidding process ends, the City Council awards the contract and staff works to ensure that the necessary paperwork and insurance documents are complete. Only then can construction begin. Though sometimes lengthy, this process ensures residents receive well-executed projects in a cost-effecitve manner.
The Public Services Department is revising the way it will be reporting the status of projects in the deisgn phase. Please check back by January 2012 for the new format.
Please contact the Engineering Division at (650) 616-7065 if you have any questions regarding the status or scope of these projects.