Construction Updates

June 2022

Water Line Installation:  The new Recreation and Aquatic Center Project's water line installation is scheduled to occur from June 27 through approximately July 29, 2022. The construction work will take place between the hours of 8:00 a.m. and 5:00 p.m., Monday through Friday. 

Traffic along Crystal Springs Road will be limited to one-lane of traffic near City Park Way.  Safety flaggers will be onsite during construction helping with traffic flow in the modified areas.  Questions? Contact Us.

May 2022

Construction activity is underway at San Bruno City Park, City Park Way and Crystal Springs Ave.  Lathrop Construction will be installing temporary construction fencing at the above noted locations to facilitate continued construction activities for the New Recreation and Aquatic Center Project.  In late June / early July, City Park Way will be closed to vehicular and pedestrian traffic.   Crystal Springs Ave. will have periodic lane closures and traffic control will be implemented to allow for utility work.  Road closures will be posted on changeable message boards near the work zones prior to start of work.  

The site work hours are 7:00AM and 6:00PM, Monday to Friday.RAC Images May  2022 Opens in new window

See the following for the construction highlights completed during the month of May:

  • Completed second phase of shoring wall
  • Certified building pads
  • Started excavation for building foundations
  • Started placing rebar for building foundations 





April 2022

RAC Images Apr  2022 Opens in new windowSee the following for the construction highlights completed during the month of April:

  • Started second phase of Shoring Wall
  • Rough graded building pads
  • Started and completed GeoPiers work at building pads
  • Started and completed crosswalk/sidewalk improvements at south edge of park 







March 2022

RAC Update Mar  2022See the following for the construction highlights completed during the month of March:

  • Grading completed at Soil Nail Shoring Wall
  • Drilling and setting of soil nails completed at Soil Nail Wall
  • Completed grouting of Soil Nail Wall with shot-crete 







February 2022

See the following for the construction highlights completed during the month of February:

  • Grading continues for Soil Nail Shoring WallRAC Images Feb  2022
  • Drilled and set soil nails at Soil Nail Wall
  • Grouted of Soil Nail Wall with shot-crete (concrete)
  • Backfilled old pool excavation







January 2022

2022JanUpdate Opens in new windowSee the following for the construction highlights completed during the month of January:

  • Removed additional trees along Crystal Springs Road
  • Completed 10'' waterline bypass with concrete collars and thrust blocks
  • Removed old waterline pipe
  • Began grading slope for Shoring Wall





December 2021

DEC2021RACBanner Opens in new windowSee the following for the construction highlights completed during the month of December:

  • Abatement completed, final report being developed
  • Trees identified for removal in January 2022
  • Contractor poised to install temporary water bypass line (delayed due to inclement weather)
  • Stoned construction entrance has been installed to limit tracking mud
  • Existing streetlights re-energized



November 2021

2021NovUpdateSee the following for the construction highlights completed during the month of November:

  • Gym Building Demolition Completed
  • Tree Removal along Crystal Springs Road and within San Bruno City Park

October 2021

October 2021 UpdateSee the following for the construction highlights completed during the month of October:

  • Pool Building Demolition Completed
  • Gym Building Demolition Ongoing
  • CM Trailer Onsite and Occupied
  • Sidewalk closed along City Park Way
  • Ramp from Crystal Springs Road to City Park Way closed


September 2021

September 2021 UpdateSee the following for the construction highlights completed during the month of September:

  • Contractors trailer placed in parking lot
  • Abatement
  • Perimeter fence installed
  • Sidewalk closed along City Park Way
  • Ramp from Crystal Springs Road to City Park Way closed
  • Partial tree removal performed
  • EarthCam site camera installer


If you have any questions or concerns, contact us at RecCenterBuild@sanbruno.ca.gov.