Recreation & Aquatic Center Project

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10

Construction Updates

Saturday, April 23, 2022

The contractor will be working this Saturday, April 23, 2022 from 8:00AM to 5:00PM to continue drilling the Geopier foundations. The work will all be performed onsite and the equipment noise is not expected to impact the surrounding area and should only heard within the project site. If you have any questions, please contact us at RecCenterBuild@sanbruno.ca.gov.


March 2022

RAC Update Mar  2022See the following for the construction highlights completed during the month of March:

  • Grading completed at Soil Nail Shoring Wall
  • Drilling and setting of soil nails completed at Soil Nail Wall
  • Completed grouting of Soil Nail Wall with shot-crete 







February 2022

See the following for the construction highlights completed during the month of February:

  • Grading continues for Soil Nail Shoring WallRAC Images Feb  2022
  • Drilled and set soil nails at Soil Nail Wall
  • Grouted of Soil Nail Wall with shot-crete (concrete)
  • Backfilled old pool excavation







January 2022

2022JanUpdateSee the following for the construction highlights completed during the month of January:

  • Removed additional trees along Crystal Springs Road
  • Completed 10'' waterline bypass with concrete collars and thrust blocks
  • Removed old waterline pipe
  • Began grading slope for Shoring Wall





December 2021

DEC2021RACBannerSee the following for the construction highlights completed during the month of December:

  • Abatement completed, final report being developed
  • Trees identified for removal in January 2022
  • Contractor poised to install temporary water bypass line (delayed due to inclement weather)
  • Stoned construction entrance has been installed to limit tracking mud
  • Existing streetlights re-energized



November 2021

2021NovUpdateSee the following for the construction highlights completed during the month of November:

  • Gym Building Demolition Completed
  • Tree Removal along Crystal Springs Road and within San Bruno City Park

October 2021

October 2021 UpdateSee the following for the construction highlights completed during the month of October:

  • Pool Building Demolition Completed
  • Gym Building Demolition Ongoing
  • CM Trailer Onsite and Occupied
  • Sidewalk closed along City Park Way
  • Ramp from Crystal Springs Road to City Park Way closed


September 2021

September 2021 UpdateSee the following for the construction highlights completed during the month of September:

  • Contractors trailer placed in parking lot
  • Abatement
  • Perimeter fence installed
  • Sidewalk closed along City Park Way
  • Ramp from Crystal Springs Road to City Park Way closed
  • Partial tree removal performed
  • EarthCam site camera installer


If you have any questions or concerns, contact us at RecCenterBuild@sanbruno.ca.gov.