The Avenues 3-1 Sewer and Water Main Replacement Project is nearly complete and will begin paving along the streets El Camino Real, Angus Ave, Easton Ave, Masson Ave, Green Dr, Sylvan Ave, Hensley Ave and Kains Ave on September 11th, 2023. The grind and patch repair process will occur between 9/11/2023 to 9/15/2023. Paving will occur between 9/18/2023 to 9/22/2023. Through access along each street may be restricted or prohibited throughout the grinding and paving process. Up to three (3) blocks may be impacted each day with grinding or paving. Please click here for the paving sequence the contractor will be following during both weeks.